Project 2019 Extension of the electricity grid in Gumda
Gumda is a small assembly village in the Gorkha district of Nepal. Located at an altitude of 2000m, it is the capital of Yamgaon where we have carried out our project for a "Yuwamai Khola" hydroelectric power plant.Following the earthquake of 2015, several houses in this village could not be rebuilt in the same place, which required their relocation to a new district. These houses are now being rebuilt but are not supplied with electricity. The village community asked us to finance this extension. The Namasté Gumda committee gave a favourable opinion on this project at the end of 2018. We are now awaiting a detailed offer from the electrical engineer and the approvals of the local authorities in order to make a final decision on the financing of this project.
Le projet en quelques chiffres:
-
60 maisons
-
250 habitants
-
20 poteaux électriques
-
6 Km de câble électrique aérien
-
CHF 9500.-
Le projet d’alimentation électrique du nouveau quartier de Gumda correspond pleinement aux critères fixés par Namasté Gumda. Grace à cette réalisation, les habitants bénéficient de l’électricité dans leurs logements et les ruelles du village sont éclairées.
Le coût du projet de 8795.- est sommes toute modeste en rapport aux bénéfices retiré par les habitants, il a été terminé à fin juillet 2019.
Télécharger l'étude complète du projet ici
Si vous souhaitez soutenir nos futures projets, faites un don
IBAN CH72 0900 0000 1419 7173 6
65946362_458823234677129_889391826394834
65814652_420445251886139_373723639356325
65946362_458823234677129_889391826394834
1/14
bottom of page