Project 2019 Extension of the electricity grid in Gumda

Gumda is a small assembly village in the Gorkha district of Nepal. Located at an altitude of 2000m, it is the capital of Yamgaon where we have carried out our project for a "Yuwamai Khola" hydroelectric power plant.Following the earthquake of 2015, several houses in this village could not be rebuilt in the same place, which required their relocation to a new district. These houses are now being rebuilt but are not supplied with electricity. The village community asked us to finance this extension. The Namasté Gumda committee gave a favourable opinion on this project at the end of 2018. We are now awaiting a detailed offer from the electrical engineer and the approvals of the local authorities in order to make a final decision on the financing of this project.

Photo_aérienne_de_Gumda.jpg

Le projet en quelques chiffres:

  • 60 maisons

  • 250 habitants

  • 20 poteaux électriques

  • 6 Km de câble électrique aérien​

  • CHF 9500.-

Le projet d’alimentation électrique du nouveau quartier de Gumda correspond pleinement aux critères fixés par Namasté Gumda. Grace à cette réalisation, les habitants bénéficient de l’électricité dans leurs logements et les ruelles du village sont éclairées.

 

Le coût du projet de 8795.- est sommes toute modeste en rapport aux bénéfices retiré par les habitants, il a été terminé à fin juillet 2019.

Télécharger l'étude complète du projet ici

 

 